Dear Owner(s) of Nimble Ziyun Mansion:
As time speeds by, good things approach. 2021 has come to an end in a flash ~ this winter, your expectation of happiness is drawing near, and the appearance of your new home is becoming clearer!
From blueprint to reality, Ningxiang • Nimble Ziyun Mansion has always focused on the greatness of a home, up to every detail. Every progress report we make will move you closer to your new home, and every ounce of effort we put will soothe every heart of expectation.
We will also be grateful for the future, and look forward to welcoming you to your sweet new home in 2022!
Nimble Ziyun·Mansion
Ready to Delivery: Enjoying a Happy Home
——Stage 1 Delivery Progress Report——
Block 3# (17F): Interior work and landscape work have been completed, and pre-delivery cleaning are underway. Ready to delivery.
Block 10# (31F): Interior work and landscape work have been completed, and pre-delivery cleaning are underway. Ready to delivery.
Block 11# (31F): Interior work and landscape work have been completed, and pre-delivery cleaning are underway. Ready to delivery.
Designed with Ingenuity, Presented with Real Beauty
——Landscape in delivery zone——
The footpath winds its way through the landscape,
based on evergreen plants
and combined with multi-level plants,
hence creating a community garden in picturesque disorder.
The plants not only luxuriate in summer,
but also showcase different seasonal sceneries.
The essence of nature can be touched while staying home.
Enjoy your good time through seasons.
Well-Crafted Residence, Attentive Showcase
——Progress Brief of Other Blocks of Stage 1——
Block 4# (17F): Exterior work, windows fitting and interior work for 1-17F have been completed, as well as outdoor landscape work. 50% of common area work has been completed.
Block 1# (3F): Indoor masonry, door-and-window frames and plastering have been completed, with refined decoration underway.
Pre-delivery cleaning under progress
Basement (-1F) of Stage 1: Indoor masonry, plastering, ceiling/wall putty, emery leveling have been completed; Fire sprinkler and ventilator have been installed;
Distribution room of Block 1# and 2# have been completed; electric and water equipment, fire pump room/equipment and water supply pump room/equipment have been completed and installed; parking space marking have been completed; wires and cables have been laid.
Create Goodness through Details, Cling to Quality with Ingenuity
——Progress of Stage 2——
The main structures of blocks of Stage 2 have been roofed.
Along with your desire for a happy life,
a new home will soon unveil.
Block 5# (31F): Indoor masonry, window frame work and plastering of 1-31F have been completed; finishing of exterior wall of 1-31F have been completed; scaffolding of 1-10F and 31-20F have been removed.
Block 6# (31F): Main structure has been roofed, and masonry work of 1-31F have been completed.
Block 9# (31F): Main structure has been roofed, and masonry work of 1-31F have been completed; interior plaster work of 2-30F have been completed; exterior plaster work of 8-15F have been completed.
Block 12# (31F): Main structure has been roofed, and masonry and plaster work of 1-31F have been completed; exterior plaster work of 1-31F have been completed; exterior finishing work of 15-2F have been completed.
Boutique may stand the test of time, leading to a happy life.
Day and night, we thank your support with ingenuity,
and strive hard to prove our capacities with quality.
Nimble Ziyun Mansion knows what you expect!
Hold quality to a harsh standard, and build ideal residence with heart.
A new home will soon unveil, and we look forward to seeing you!